Lotus Resources has produced the first U3O8 [“yellowcake”] from its 85%-owned Kayelekera Uranium Mine in Malawi. This major milestone is a key final step in Kayelekera’s successful processing plant commissioning, […]
Read MoreLotus Resources restarts operations at Malawi’s Kayelekera Uranium Mine
Lotus Resources has officially relaunched the Kayelekera uranium mine in Malawi, marking a significant milestone for the country’s mining sector and its local communities. The restart, inaugurated by President Dr […]
Read MoreLotus gets green light for Kayelekera restart
Lotus Resources Limited has received the final regulatory approval required to advance the restart of its Kayelekera Uranium Project in Malawi. The certificate, issued to Lotus (Africa) Limited—an 85%-owned subsidiary […]
Read MoreLotus Resources begins high-grade ore processing at Kayelekera
Lotus Resources Limited has commenced high-grade ore processing at its flagship Kayelekera Uranium Project in Malawi, which is a key milestone as the company prepares for first uranium production this […]
Read MoreLotus to receive environmental certificate for Kayelekera
Lotus Resources Limited has received confirmation from the Malawi Environment Protection Authority (MEPA) that its 85%-owned subsidiary, Lotus (Africa) Limited, will be issued the Environmental and Social Impact Assessment (ESIA) […]
Read MoreLotus enters final phase of commissioning at Kayelekera
Lotus Resources Limited has begun hot commissioning at its Kayelekera Uranium Project in Malawi after successfully restarting a key milling facility, keeping the company on schedule to deliver its first […]
Read MoreLotus enters final phase of commissioning at Kayelekera
Lotus Resources Limited has begun hot commissioning at its Kayelekera Uranium Project in Malawi after successfully restarting a key milling facility, keeping the company on schedule to deliver its first […]
Read MoreLotus advances Kayelekera uranium with first mill feed
Lotus Resources Limited is completing process plant refurbishment work on its Kayelekera Uranium Project in Malawi, with the first product expected this quarter. Highlights: Kayelekera SAG mill refurbishment completed, grinding […]
Read MoreLotus advances Kayelekera commissioning, targets Q3 restart
Lotus Resources Limited has advanced its Kayelekera Uranium Project in Malawi, with cold commissioning advanced and production on track for Q3 2025. The company has adopted an owner-operator mining model. […]
Read More